P. W. Moss & Associates |
|
Engineers - Project Managers - Owner's Representatives - Construction Managers |
|
Current Project Bidding |
|
Endeavor Elementary School Construction Manager: P.W. Moss & Associates Architect: Netta Architects Bids were received at the North Hanover Township Board of Education Offices, 331 Monmouth Road, Wrightstown, NJ 08562, on May 2, 2017 and the results are as follows: Updated May 2, 2017 All results are unofficial |
|
General Construction |
|
|
|
|
|
|
|
|
|
|
Bidder |
Base Bid |
Alt #1 |
Alt #2 |
Alt #3 |
Alt #4 |
Alt #5 |
Alt #6 |
Alt #7 |
Alt #8 |
|
Boro Construction |
$26,472,000 |
$237,153 |
$99,296 |
$1,846 |
$0 |
$0 |
$0 |
-$171,700 |
-$31,700 |
|
G & P Parlamus |
$29,371,000 |
$325,000 |
$100,000 |
$1,500 |
$0 |
$0 |
$0 |
-$170,000 |
-$30,000 |
|
Dobco, Inc. |
$29,775,000 |
$260,000 |
$35,000 |
$0 |
$0 |
$0 |
$0 |
-$175,000 |
$35,000 |
|
Niram, Inc. |
$30,883,000 |
$480,000 |
$40,000 |
$1,000 |
$0 |
$0 |
$0 |
-$315,000 |
-$200,000 |
|
Danadrea Construction |
$31,513,000 |
$307,000 |
$120,000 |
$2,000 |
$485,000 |
$485,000 |
$485,0000 |
-$171,700 |
-$31,700 |
|
Del-Sano Corp, |
$33,608,553 |
$223,655 |
$38,850 |
$550 |
$0 |
$0 |
No bid |
-$53,052 |
-$322,350 |
|
Ernest Bock & Sons |
$34,785,000 |
$300,000 |
$98,500 |
$1,600 |
$0 |
$0 |
$0 |
-$54,000 |
-$31,700 |
|
Structural Steel |
|
|
|
|
|
|
|
|
|
|
Bidder |
Base Bid |
Alt #1 |
|
|
|
|
|
|
|
|
Arnold Steel Co. |
$5,530,000 |
$330,000 |
|
|
|
|
|
|
|
|
RC Fabricators |
$6,000,000 |
$463,000 |
|
|
|
|
|
|
|
|
Mechanical |
|
|
|
|
|
|
|
|
|
|
Bidder |
Base Bid |
Alt #1 |
Alt #2 |
Alt #3 |
Alt #4 |
|
|
|
|
|
Boro Construction |
$6,050,000 |
$790,000 |
$700,000 |
No bid |
No bid |
|
|
|
|
|
Preferred Mechanical |
$6,390,000 |
$821,000 |
$873,000 |
$861,000 |
$823,000 |
|
|
|
|
|
GBI Inc/Thermal Piping |
$6,986,000 |
$793,000 |
$660,00 |
$672,000 |
$660,000 |
|
|
|
|
|
Barham Group |
$7,663,000 |
$0 |
$75,000 |
$100,000 |
$75,000 |
|
|
|
|
|
Falasca Mechanical |
$7,546000 |
$816,000 |
$836,000 |
$836,000 |
$826,000 |
|
|
|
|
|
Framan Mechanical |
$8,955,000 |
$806,000 |
$920,000 |
$955,000 |
$1040,000 |
|
|
|
|
|
Thassian Mechanical |
$9,836,000 |
$0 |
$100,000 |
$100,000 |
$0 |
|
|
|
|
|
Electrical |
|
|
|
|
|
|
|
|
|
|
Bidder |
Base Bid |
Alt #1 |
|
|
|
|
|
|
|
|
MJF Electrical |
$3,620,000 |
$30,000 |
|
|
|
|
|
|
|
|
Boro Construction |
$4,324,000 |
$25,000 |
|
|
|
|
|
|
|
|
DEC Electrical Contr |
$4,474,400 |
$28,400 |
|
|
|
|
|
|
|
|
Philips Brothers |
$4,894,323 |
$29,600 |
|
|
|
|
|
|
|
|
PJ Smith Electric |
$5,310,000 |
$31,100 |
|
|
|
|
|
|
|
|
Breaker electric |
$5,750,000 |
$25,000 |
|
|
|
|
|
|
|
|
Eastern Construction |
$7,750,000 |
$50,000 |
|
|
|
|
|
|
|
|
Plumbing |
|
|
|
|
|
|
|
|
|
|
Bidder |
Base Bid |
Alt #1 |
|
|
|
|
|
|
|
|
CJ Schmidt & Sons |
$2,305,800 |
$850 |
|
|
|
|
|
|
|
|
Preferred Mechanical |
$2,369,000 |
$8,500 |
|
|
|
|
|
|
|
|
Kaser Mechanical |
$2,560,000 |
$14,000 |
|
|
|
|
|
|
|
|
Bayshore Mechanical |
$2,774,000 |
$24,000 |
|
|
|
|
|
|
|
|
Annese Mechanical |
$3,139,000 |
$0 |
|
|
|
|
|
|
|